Case Study  ·  Technology Scouting

Vetting new ways to build a refinery.

A major oil and gas company and its project developer wanted deployable technologies to make a refinery upgrade faster, safer and higher quality. We scouted beyond their own list, valued each option by NPV and helped choose what to implement.

The Client

The client is a major oil and gas company working on a refinery upgrade project. It wanted new technologies that improve construction efficiency, lead times, safety and quality.

The Challenge

A long wish list.
Find what pays off.

Prescouter was asked to find immediately deployable technologies across construction, digital, safety, robotics, modularization, non-metallics and energy optimization, and to compare their value using net present value.

  • Speed

    Shorter lead times

    Build faster with fewer delays.

  • Safety

    Safer workplaces

    Reduce risk for crews on site.

  • Value

    Positive NPV

    Prove the case over 30 years.

Our Approach

Scouting weekly and valuing every option.

Weekly meetings
18client meetings held

Scout every week

We brought 5 to 10 technologies to each weekly meeting, shaped by the client’s pain points.

Vendor outreach
71technologies taken deeper

Reach the vendors

Our outreach team gathered pricing and cost data from vendors for the most promising options.

NPV modeling
3timelines modeled

Value each option

We estimated net present value over 5, 17 and 30 years across project and operations phases.

The Outcome

From a long list to the build plan.

Prescouter presented 108 technologies across 7 research rounds and valued both its own picks and 73 client-identified options by NPV. In total, 45 client technologies and 11 Prescouter technologies were chosen for implementation, and vendor demos followed.

  • Scope

    108 technologies

    Presented over 7 rounds of research.

  • Selection

    11 Prescouter picks

    Chosen for implementation alongside 45 more.

  • Adoption

    4-part rollout approach

    Flexibility, accountability, awareness, incentives.

The best construction ideas often sit outside a project’s original list. Pairing open scouting with a clear NPV case makes them easier to adopt.

Let’s Talk

Which technologies could speed up your build?

Scout widely, value each option and focus on what pays off on site. Wherever you’re starting from, we’ll help you get there.

Or email [email protected]

Book a Session

Want to skip the email back-and-forth?

Pick a time on our calendar right now.

If you’d like to know the outcome of your submission, please leave your email address